Team experience

138 kV AIS substation, five bays

Utility · United States · 2024

Need and scope

A utility needed a coordinated 3D model and updated plan sets for an air-insulated substation with five bays. The in-house team had the engineering knowledge but lacked Revit modeling capacity for the full equipment count.

Input documentation

2D drawings in DWG, single-line diagram, equipment datasheets.

Work executed

Equipment, structures, bus, grounding and cable trench layout modeled in Revit. Equipment families (transformers, breakers, disconnect switches, instrument transformers) built from datasheets and placed per the single-line diagram.

Deliverables

Revit 3D model, plan/section/elevation sheets, clash review file for Navisworks, native RVT.

This work was performed by our engineers at previous employers. It is not a BIM Eléctrico LLC client project.

Aerial 3D render of an air-insulated utility substation with multiple bays, transformers and steel gantries

Your project. Our expertise. Let's talk.

Tell us what your team needs and the milestone you are working toward. We'll review whether a focused pilot is a suitable starting point.